Establishment Background and Plans
  • JAN 2007 : Confirmation of the building site
  • Project period : 2010. 01 ~ 2013. 08
  • Project cost : KRW 41.7 billion
  • Lot area : 74,272㎡
  • Gross floor area : 11,086.34㎡
Present HISTORY

2021

  • 4.12~19Architectural design competition (digital cultural complex)
Architectural design competition (digital cultural complex)

2013

  • 11.22Opening ceremony
Opening ceremony

2013

  • 08.31Construction completion
Construction completion

2013

  • 08.Installation of fences and sidewalks outside the museum
Installation of fences and sidewalks outside the museum

2013

  • 08.07Laying of reinforced concrete for the garden walkway
Laying of reinforced concrete for the garden walkway

2013

  • 04.25Compaction work for the sub-base layers of the parking lot and internal road
Compaction work for the sub-base layers of the parking lot and internal road

2013

  • 04.25Artificial soil layer construction for the Sky Garden
Artificial soil layer construction for the Sky Garden

2013

  • 03.27Aggregate laying and compaction work for the garden walkway사
Aggregate laying and compaction work for the garden walkway

2012

  • 12.30Construction of Tteurak Garden
Construction of Tteurak Garden

2012

  • 10.30Installation of metal louvers in the exhibition hall
Installation of metal louvers in the exhibition hall

2012

  • 10.23Installation of rooftop drainage boards
Installation of rooftop drainage boards

2012

  • 09.15Finishing work on the ceiling
Finishing work on the ceiling

2012

  • 07.15Installation of windows
Installation of windows

2012

  • 07.02Construction of the machine room and firefighting piping facility on B2
Construction of the machine room and firefighting piping facility on B2

2012

  • 06.30Exterior construction
    -Installation of rain screens for curved areas
    -Glass fiber reinforced concrete work
Exterior construction

2012

  • 03.Insulation and moisture-proofing work on the exhibition halls and storage rooms
Insulation and moisture-proofing work on the exhibition halls and storage rooms

2011

  • 12.30Framework of the outdoor restrooms
Framework of the outdoor restrooms

2011

  • 10.14Steel framework of B1 and above-ground floors
Steel framework of B1 and above-ground floors

2011

  • 11.04Foundation concrete work for the storage rooms
Foundation concrete work for the storage rooms

2010

  • 12.15Groundbreaking ceremony
Groundbreaking ceremony

2007 ~ 2008

  • 09~02 Architectural design competition
Architectural design competition
2007.01 Confirmation of the building site